Rim Rock Road project

Timeline: 1. Finish pulverizing 10/10. 2. Trees removed by 10/11.  3. Crossing culverts 10/15 – 10/16.  4. Road repositioning 10/14 to 10/18.  5. Paving around 10/25.  6. Driveway culverts week of 10/28.  7. Shouldering after culverts.  8. Restoration after culverts.