Timeline: 1. Finish pulverizing 10/10. 2. Trees removed by 10/11. 3. Crossing culverts 10/15 – 10/16. 4. Road repositioning 10/14 to 10/18. 5. Paving around 10/25. 6. Driveway culverts week of 10/28. 7. Shouldering after culverts. 8. Restoration after culverts.